65 WATSONS LANE CULVERT [2023] - C15-77-23 (S)
68-70 BROOKSTREAM CRT [2023] - C15-09-24 (H)
BARTON ST - PARKDALE TO TALBOT [2022] - C15-02-22 (HSW)
BRAMPTON ST CENTRE ISLAND AND BOULEVARD RESTORATION (STRATHEARNE TO PARKDALE) [2023] - C15-67-23 (H)
BRIDGE 050 - THIRD RD E, 1000M SOUTH OF RIDGE RD [2023] - C15-19-23 (BR)
BRIDGE 105 - BOOK RD W, 330M WEST OF TRINITY RD S [2023] - C15-19-23 (BR)
BRIDGE 111 - MINERAL SPRINGS RD, 65 METRES WEST OF MARTIN RD [2023] - C15-26-23 (BR)
BRIDGE 119 - WOODBURN RD, 750 METRES SOUTH OF REGIONAL 20 RD [2023] - C15-37-23 (BR)
BRIDGE 296 - GOVERNORS RD, 45 METRES EAST OF OGILVIE ST & GOVERNORS RD REHABILITATION, MAIN TO 100M WEST OF OGILVIE [2023] - C15-20-23 (BRHW)
BRIDGE 342 - WESTOVER RD, 245 METRES NORTH OF HIGHWAY NO. 8 [2023] - C15-05-23 (BR)
CANADA COMMUNITY-BUILDING FUND ADDITIONAL $30M: ACADEMY ST / GOLFDALE PL (WITHIN ST. JOHN'S NEIGHBOURHOOD) [2022] - C15-57-22 (H)
CANADA COMMUNITY-BUILDING FUND ADDITIONAL $30M: AVALON AVE / BRANDOW CRT / CHARLES ST / RANDALL AVE (WITHIN BATTLEFIELD NEIGHBOURHOOD) [2023] - C15-13-23 (H)
CANADA COMMUNITY-BUILDING FUND ADDITIONAL $30M: CHURCH ST (WITHIN ST. JOHN'S NEIGHBOURHOOD) [2022] - C15-57-22 (H)
CANADA COMMUNITY-BUILDING FUND ADDITIONAL $30M: CRESTVIEW AVE / TERRENCE PARK DR (WITHIN CLEARVIEW NEIGHBOURHOOD) [2022] - C15-57-22 (H)
CANADA COMMUNITY-BUILDING FUND ADDITIONAL $30M: EAST ST N - HUNTER ST TO YORK RD [2023] - C15-30-23 (HW)
CANADA COMMUNITY-BUILDING FUND ADDITIONAL $30M: FAIRFIELD AVE - BRITANNIA AVE TO BARTON ST E [2023] - C15-12-23 (HSW)
CANADA COMMUNITY-BUILDING FUND ADDITIONAL $30M: GATESTONE DR - SHADYGLEN DR TO ISAAC BROCK DR [2022] - C15-62-22 (H)
CANADA COMMUNITY-BUILDING FUND ADDITIONAL $30M: HAMILTON ST - DUNDAS ST TO SILVER CRT [2022] - C15-60-22 (H)
CANADA COMMUNITY-BUILDING FUND ADDITIONAL $30M: HOWARD BLVD / THOMSON DR, 90M WEST OF MAYS CRES TO MAIN ST S [2022] - C15-60-22 (H)
CANADA COMMUNITY-BUILDING FUND ADDITIONAL $30M: KIRKENDALL BIKE BLVD PILOT - KENT ST AND PEARL ST [2022] - C15-69-22 (H)
CANADA COMMUNITY-BUILDING FUND ADDITIONAL $30M: MAPLE DR / SPARTAN AVE [2023] - C15-41-23 (H)
CANADA COMMUNITY-BUILDING FUND ADDITIONAL $30M: MORDEN ST - LOCKE ST N TO PEARL ST N [2023] - C15-03-23 (HSW)
CANADA COMMUNITY-BUILDING FUND ADDITIONAL $30M: STRATHCONA BIKE BLVD PILOT - BREADALBANE ST AND JONES ST [2022] - C15-69-22 (H)
CLAREMONT ACCESS - STEEL FACING WALLS REMOVAL (3, 3A, 4 & 4A) [2023] - C15-51-23 (H)
CONSTRUCT PEDESTRIAN CROSSOVER (PXO): LIMERIDGE RD W & ELGAR AVE [2023] - C15-45-23(TR)
CONSTRUCT TRAFFIC SIGNAL UNDERGROUND: QUEENSTON RD & KENORA/GREENFORD (SIGNAL MODERNIZATION) [2022] - C15-41-22(TR)
CONSTRUCT TRAFFIC SIGNAL UNDERGROUND: WELLINGTON STREET & HUNTER STREET [2023] - C15-45-23(TR)
CONSTRUCT TRAFFIC SIGNAL UNDERGROUND: YORK ROAD & OLYMPIC DRIVE (FULL SIGNAL) [2023] - C15-45-23(TR)
CONSTRUCTION OF NEW IPS INFRASTRUCTURE: MAIN ST E AT ALBERT STREET [2023] - C15-45-23(TR)
CONSTRUCTION OF NEW IPS INFRASTRUCTURE: MAIN ST E AT HILDA AVE [2023] - C15-45-23(TR)
DEWITT RD - HIGHWAY 8 TO BARTON ST [2023] - C15-02-23 (HS), C15-76-21 (HS)
DICKENSON RD - UPPER JAMES ST TO UPPER CENTENNIAL PKWY [2022] - C15-11-22 (HSW)
GARROW DR - CRANBROOK DR TO GARTH ST [2023] - C15-15-23 (H)
HIGHLAND RD W - GLENHOLLOW DR TO FIRST RD W [2022] - C15-62-22 (H)
HIGHLAND RD W - WINTERBERRY DR TO GLENHOLLOW DR [2022] - C15-62-22 (H)
INSTALLATION OF TYPE D PXO - HARBOUR FRONT DRIVE AND MARINA ACCESS ROADWAY. [2023] - C15-45-23(TR)
IPS/PXO INSTALLATION: SANFORD AVENUE & HURON STREET [2023] - C15-45-23(TR)
JAMES ST S VOID ADJACENT TO #'S 18, 28 & 32, BETWEEN MAIN ST AND KING ST - INVESTIGATION AND REPAIR [2023] - RFQ-01-22
JONES ST - DUNDURN ST N TO WEST END [2023] - C15-24-23 (HSW)
KENILWORTH ACCESS - ROCKFALL DRAPERY MESH [2023] - C15-71-22 (H)
KIRBY AVE - HIGHWAY NO. 8 TO EAST END OF STREET & HUNTS DR - KIRBY AVE TO EAST END OF STREET [2022] - C15-63-22 (H)
LARGE DIAMETER WATERMAIN REHABILIITATION: KENILWORTH RESERVOIR TUNNEL WATERMAIN [2023] - C13-10-22
LARGE VALVE INSTALLATION: NORTH OF THE GREENHILL RESERVOIR (HDR1B) [2023] - C15-43-22 (W)
LARGE VALVE REPLACEMENT (HC10V055, HC10V054,HC11V052, HD06V031,HD09V051, HC11V050 AND HD13V056): FENNELL AT EAST 12TH, EAST 17TH ST, AT UP WENTWORTH, AT EAST 34TH, AT UPPER OTTAWA, AND S/O SANDALWOOD [2023] - C15-68-22 (W)
MARION AVE - LONGWOOD RD S TO DROMORE CRES [2023] - C15-28-23 (HW)
MOUNTAIN PARK AVE PHASE 01 - UPPER WENTWORTH ST TO PARKING LOT EAST OF POPLAR AVE, AND MOUNTAIN BROW TRAIL ENHANCEMENTS (WITHIN EASTMOUNT NEIGHBOURHOOD) [2023] - C15-34-22 (HW)
OSLER DRIVE OUTFALL AT GRANT BLVD [2023] - C15-16-23 (S)
RETAINING WALL RW0447 - WEIRS LANE, 392M NORTH OF JOHNSON AVE - W/S [2023] - C15-49-23 (H)
SATELLITE CITY TRUNK PIPELINE CIPP REHABILITATION FROM MUD ST W TO QUIGLEY RD (NORTH OF VEEVERS DR) [2022] - C13-22-19 (2022)
SCENIC DR - MOHAWK TO CHATEAU [2023] - C15-59-23 (HS)
SEWER REGULATOR REHABILITATION [2023] - C15-52-23 (IR)
SHERMAN - WILSON TO SOUTH END (LRT-ENABLING) [2023] - C15-32-23 (HW)
SOUTHCOTE RD - GARNER RD (EXCLUDING INTERSECTION OF GARNER RD) TO HWY 403 [2022] - C15-19-22 (HSW)
TRAFFIC SIGNAL MODIFICATION AND ASSOCIATED WORKS: PRITCHARD RD & RYMAL ROAD [2023] - C15-45-23(TR)
WATERMAIN STRUCTURAL LINING: HILLYARD ST TO WENTWORTH ST N [2023] - C13-01-20 (2023)
WATERMAIN STRUCTURAL LINING: OTTAWA ST S/ LONDON ST S/ EDGEMONT ST S [2023] - C13-01-20 (2023)
WATERMAIN STRUCTURAL LINING: PARK ROW S - LAWRENCE RD TO MAPLE AVE [2023] - C13-01-20 (2023)
WATERMAIN STRUCTURAL LINING: WEST 19TH ST - MOHAWK RD W TO ELMWOOD AVE [2023] - C13-01-20 (2023)
WATERMAIN STRUCTURAL LINING:GLOVER RD - 50M NORTH OF GLOVER ACCESS RD S TO 482 GLOVER RD [2023] - C13-01-20 (2023)
WATERMAIN STRUCTURAL LINING:SOUTH DR - HWY 5 W TO SOUTH END [2023] - C13-01-20 (2023)
WELLINGTON ST STORM OUTFALL - BURLINGTON ST - HARBOUR [2023] - C15-53-22 (IR)
Select A Year
All Years
2022
2023
Project Name
Ward
All Wards
Ward 1
Ward 2
Ward 3
Ward 4
Ward 5
Ward 6
Ward 7
Ward 8
Ward 9
Ward 10
Ward 11
Ward 12
Ward 13
Ward 14
Ward 15
65 WATSONS LANE CULVERT [2023] - C15-77-23 (S)
Map
Storm
Culvert replacememnt
Estimated Cost
$300,000.00
Contact
[email protected]
68-70 BROOKSTREAM CRT [2023] - C15-09-24 (H)
Map
Other
68-70 BROOKSTREAM COURT SLOPE STABILIZATION AND PRIVACY BARRIER
Estimated Cost
$500,000.00
Contact
[email protected]
BARTON ST - PARKDALE TO TALBOT [2022] - C15-02-22 (HSW)
Map
Road
Road and sidewalk reconstruction
Sewer Service Line
Sanitary Service Lateral Replacements
Storm
Storm Collection System Expansion
Water
Water System Distribution Replacement
Contractor
Coco Paving Inc
Start Date
Jul 31, 2022
Estimated Construction
Aug 2022 - Jul 2024
Actual Cost
$9,048,000.00
Contact
[email protected]
BRAMPTON ST CENTRE ISLAND AND BOULEVARD RESTORATION (STRATHEARNE TO PARKDALE) [2023] - C15-67-23 (H)
Map
Road
Restoration of centre islands and boulevards
Contractor
Royal Ready Construction Ltd.
Start Date
Aug 8, 2023
Estimated Construction
Aug 2023 - Oct 2023
Actual Cost
$328,100.00
Contact
[email protected]
BRIDGE 050 - THIRD RD E, 1000M SOUTH OF RIDGE RD [2023] - C15-19-23 (BR)
Map
Structure
Culvert Rehabilitation
Contractor
Anthony's Excavating Central Inc.
Start Date
Jul 4, 2023
End Date
Sep 19, 2023
Actual Cost
$345,000.00
Contact
[email protected]
BRIDGE 105 - BOOK RD W, 330M WEST OF TRINITY RD S [2023] - C15-19-23 (BR)
Map
Structure
Culvert Rehabilitation
Contractor
Anthony's Excavating Central Inc.
Start Date
Jul 19, 2023
End Date
Sep 19, 2023
Actual Cost
$355,000.00
Contact
[email protected]
BRIDGE 111 - MINERAL SPRINGS RD, 65 METRES WEST OF MARTIN RD [2023] - C15-26-23 (BR)
Map
Structure
Culvert Rehabilitation
Contractor
Green Infrastructure Partners Inc. (GIP)
Start Date
Aug 21, 2023
End Date
Sep 25, 2023
Actual Cost
$743,000.00
Contact
[email protected]
BRIDGE 119 - WOODBURN RD, 750 METRES SOUTH OF REGIONAL 20 RD [2023] - C15-37-23 (BR)
Map
Structure
Structure Rehabilitation
Contractor
Lancoa Contracting
Start Date
Jul 15, 2023
End Date
Sep 30, 2023
Actual Cost
$190,000.00
Contact
[email protected]
BRIDGE 296 - GOVERNORS RD, 45 METRES EAST OF OGILVIE ST & GOVERNORS RD REHABILITATION, MAIN TO 100M WEST OF OGILVIE [2023] - C15-20-23 (BRHW)
Map
Location(s)
GOVERNOR'S RD
From
START OF BRIDGE
To
END OF BRIDGE (45 meters east of OGILVIE ST)
Road
Road and sidewalk reconstruction
Structure
Bridge Rehabilitation
Structure
Sanitary Sewer Pipe Bridge Rehab
Water
Water Distribution System Replacement
Contractor
Seawaves Development Services Inc.
Start Date
Jun 26, 2023
Estimated Construction
Jun 2023 - Nov 2023
Actual Cost
$4,331,000.00
Contact
[email protected]
BRIDGE 342 - WESTOVER RD, 245 METRES NORTH OF HIGHWAY NO. 8 [2023] - C15-05-23 (BR)
Map
Structure
Bridge Rehabilitation
Contractor
Urbanlink Civil Ltd.
Start Date
Aug 21, 2023
Estimated Construction
Aug 2023 - Dec 2023
Actual Cost
$872,000.00
Contact
[email protected]
CANADA COMMUNITY-BUILDING FUND ADDITIONAL $30M: ACADEMY ST / GOLFDALE PL (WITHIN ST. JOHN'S NEIGHBOURHOOD) [2022] - C15-57-22 (H)
Map
Road
Road resurfacing
Contractor
Rankin Construction Inc.
Start Date
Sep 27, 2022
End Date
Jun 14, 2023
Actual Cost
$466,000.00
Contact
[email protected]
CANADA COMMUNITY-BUILDING FUND ADDITIONAL $30M: AVALON AVE / BRANDOW CRT / CHARLES ST / RANDALL AVE (WITHIN BATTLEFIELD NEIGHBOURHOOD) [2023] - C15-13-23 (H)
Map
Road
Road resurfacing
Contractor
Associated Paving & Materials Ltd.
Start Date
Sep 5, 2023
Estimated Construction
Sep 2023 - Nov 2023
Actual Cost
$1,250,000.00
Contact
[email protected]
CANADA COMMUNITY-BUILDING FUND ADDITIONAL $30M: CHURCH ST (WITHIN ST. JOHN'S NEIGHBOURHOOD) [2022] - C15-57-22 (H)
Map
Road
Road resurfacing
Contractor
Rankin Construction Inc.
Start Date
Sep 27, 2022
End Date
Jun 14, 2023
Actual Cost
$300,000.00
Contact
[email protected]
CANADA COMMUNITY-BUILDING FUND ADDITIONAL $30M: CRESTVIEW AVE / TERRENCE PARK DR (WITHIN CLEARVIEW NEIGHBOURHOOD) [2022] - C15-57-22 (H)
Map
Road
Road rehabilitation
Contractor
Rankin Construction Inc.
Start Date
Sep 27, 2022
End Date
Jun 14, 2023
Actual Cost
$280,000.00
Contact
[email protected]
CANADA COMMUNITY-BUILDING FUND ADDITIONAL $30M: EAST ST N - HUNTER ST TO YORK RD [2023] - C15-30-23 (HW)
Map
Road
Road reconstruction
Sewer Service Line
Sewer Service Line Replacement
Water
Watermain Replacement
Contractor
Briduco Enterprises
Start Date
Sep 11, 2023
Estimated Construction
Sep 2023 - Aug 2024
Actual Cost
$1,787,000.00
Contact
[email protected]
CANADA COMMUNITY-BUILDING FUND ADDITIONAL $30M: FAIRFIELD AVE - BRITANNIA AVE TO BARTON ST E [2023] - C15-12-23 (HSW)
Map
Road
Road reconstruction
Sewer Service Line
Sanitary service line replacement.
Water
Watermain replacement.
Contractor
KADA Group Inc.
Start Date
Jul 17, 2023
Estimated Construction
Jul 2023 - Dec 2023
Actual Cost
$1,596,145.00
Contact
[email protected]
CANADA COMMUNITY-BUILDING FUND ADDITIONAL $30M: GATESTONE DR - SHADYGLEN DR TO ISAAC BROCK DR [2022] - C15-62-22 (H)
Map
Road
Road resurfacing
Contractor
Green Infrastructure Partners Inc. (GIP)
Start Date
Sep 1, 2023
End Date
Sep 1, 2023
Actual Cost
$1,206,000.00
Contact
[email protected]
CANADA COMMUNITY-BUILDING FUND ADDITIONAL $30M: HAMILTON ST - DUNDAS ST TO SILVER CRT [2022] - C15-60-22 (H)
Map
Road
Road rehabilitation
Contractor
KING Paving & Construction (KPM Industries Ltd.)
Start Date
Nov 1, 2022
End Date
Jun 23, 2023
Actual Cost
$184,000.00
Contact
[email protected]
CANADA COMMUNITY-BUILDING FUND ADDITIONAL $30M: HOWARD BLVD / THOMSON DR, 90M WEST OF MAYS CRES TO MAIN ST S [2022] - C15-60-22 (H)
Map
Road
Road rehabilitation
Contractor
KING Paving & Construction (KPM Industries Ltd.)
Start Date
Nov 1, 2022
End Date
Jun 23, 2023
Actual Cost
$918,000.00
Contact
[email protected]
CANADA COMMUNITY-BUILDING FUND ADDITIONAL $30M: KIRKENDALL BIKE BLVD PILOT - KENT ST AND PEARL ST [2022] - C15-69-22 (H)
Map
Road
Road rehabilitation and bike blvd pilot
Traffic
Bike blvd
Contractor
Associated Paving & Materials Ltd.
Start Date
Oct 11, 2022
End Date
Jun 9, 2023
Actual Cost
$679,100.00
Contact
[email protected]
CANADA COMMUNITY-BUILDING FUND ADDITIONAL $30M: MAPLE DR / SPARTAN AVE [2023] - C15-41-23 (H)
Map
Road
Road resurfacing
Contractor
Green Infrastructure Partners Inc. (GIP)
Start Date
Aug 8, 2023
End Date
Nov 1, 2023
Actual Cost
$1,510,000.00
Contact
[email protected]
CANADA COMMUNITY-BUILDING FUND ADDITIONAL $30M: MORDEN ST - LOCKE ST N TO PEARL ST N [2023] - C15-03-23 (HSW)
Map
Road
Road reconstruction
Sanitary
Abandonment
Water
Watermain Upgrade
Contractor
Wesroc Construction Ltd.
Start Date
Oct 2, 2023
End Date
Nov 24, 2023
Actual Cost
$776,000.00
Contact
[email protected]
CANADA COMMUNITY-BUILDING FUND ADDITIONAL $30M: STRATHCONA BIKE BLVD PILOT - BREADALBANE ST AND JONES ST [2022] - C15-69-22 (H)
Map
Road
Mill to approximately 80mm depth and replace asphalt: Breadalbane from King St. to Jones St. Jones St. from Breadalbane to Woodbine Cres. (~50m) Concrete repairs as required along section of resurfacing only. Â
Traffic
Bike Blvd
Contractor
Associated Paving & Materials Ltd.
Start Date
Oct 11, 2022
End Date
Jun 9, 2023
Actual Cost
$725,000.00
Contact
[email protected]
CLAREMONT ACCESS - STEEL FACING WALLS REMOVAL (3, 3A, 4 & 4A) [2023] - C15-51-23 (H)
Map
Structure
Bin Wall Removal
Contractor
Rankin Construction Inc.
Start Date
Jun 19, 2023
Estimated Construction
Jun 2023 - Nov 2023
Actual Cost
$4,797,200.00
Contact
[email protected]
CONSTRUCT PEDESTRIAN CROSSOVER (PXO): LIMERIDGE RD W & ELGAR AVE [2023] - C15-45-23(TR)
Map
Location(s)
LIMERIDGE RD W
From
ELGAR AVE
To
ELGAR AVE (East Leg of intersection)
Traffic
Install 'Type C' Pedestrian Crossover (PXO) at the intersection of Limeridge Rd W & Elgar Ave.
Estimated Construction
May 2023 - Jun 2024
Contact
[email protected]
CONSTRUCT TRAFFIC SIGNAL UNDERGROUND: QUEENSTON RD & KENORA/GREENFORD (SIGNAL MODERNIZATION) [2022] - C15-41-22(TR)
Map
Traffic
Construct Traffic Signal Underground:Â Queenston Rd & Kenora/Greenford (Signal Modernization)
Contractor
Decew Construction Inc.
Start Date
Aug 1, 2022
End Date
Jun 26, 2023
Contact
[email protected]
CONSTRUCT TRAFFIC SIGNAL UNDERGROUND: WELLINGTON STREET & HUNTER STREET [2023] - C15-45-23(TR)
Map
Traffic
Construct underground traffic singal infrastructure in preperation for full signal installation with AODA compliance. BP
Estimated Construction
Aug 2023 - Aug 2024
Contact
[email protected]
CONSTRUCT TRAFFIC SIGNAL UNDERGROUND: YORK ROAD & OLYMPIC DRIVE (FULL SIGNAL) [2023] - C15-45-23(TR)
Map
Traffic
Construct Traffic Signal Underground: York Road & Olympic Drive (Full Signal)
Estimated Construction
Aug 2023 - Sep 2023
Contact
[email protected]
CONSTRUCTION OF NEW IPS INFRASTRUCTURE: MAIN ST E AT ALBERT STREET [2023] - C15-45-23(TR)
Map
Traffic
Installation of IPS at the intersection of Main St and Albert St. IPS infrastructure will make use to temporary wooden poles in anticipation of Main St conversion
Estimated Construction
Sep 2023 - Dec 2023
Contact
[email protected]
CONSTRUCTION OF NEW IPS INFRASTRUCTURE: MAIN ST E AT HILDA AVE [2023] - C15-45-23(TR)
Map
Traffic
Installation of IPS at the intersection of Main St and Hilda Ave. IPS infrastructure will make use to temporary wooden poles in anticipation of Main St conversion
Estimated Construction
Sep 2023 - Dec 2023
Contact
[email protected]
DEWITT RD - HIGHWAY 8 TO BARTON ST [2023] - C15-02-23 (HS), C15-76-21 (HS)
Map
Road
Road rehabilitation
Sanitary
Sanitary Sewer Replacement
Contractor
Deso Construction
Start Date
Jun 5, 2023
End Date
Nov 2, 2023
Actual Cost
$7,154,200.00
Contact
[email protected]
DICKENSON RD - UPPER JAMES ST TO UPPER CENTENNIAL PKWY [2022] - C15-11-22 (HSW)
Map
Location(s)
DICKENSON RD E (UPPER JAMES ST TO MILES RD)
Other
Project Objective:To provide external servicing to the airport lands as per Citywide Water/Wastewater Master Plan.
Road
Road resurfacing
Sanitary
Trunk Sewer Construction
Water
Water System Improvements
Contractor
Technicore
Start Date
Oct 3, 2022
Estimated Construction
Jul 2022 - Nov 2026
Actual Cost
$114,127,000.00
Contact
[email protected]
GARROW DR - CRANBROOK DR TO GARTH ST [2023] - C15-15-23 (H)
Map
Road
Road resurfacing
Storm
Catch Basin Repair
Contractor
Green Infrastructure Partners Inc. (GIP)
Start Date
Jul 28, 2023
End Date
Aug 25, 2023
Actual Cost
$366,300.00
Contact
[email protected]
HIGHLAND RD W - GLENHOLLOW DR TO FIRST RD W [2022] - C15-62-22 (H)
Map
Road
Road resurfacing
Contractor
Green Infrastructure Partners Inc. (GIP)
Start Date
Mar 29, 2023
End Date
Sep 1, 2023
Actual Cost
$2,186,000.00
Contact
[email protected]
HIGHLAND RD W - WINTERBERRY DR TO GLENHOLLOW DR [2022] - C15-62-22 (H)
Map
Road
Road resurfacing
Contractor
Green Infrastructure Partners Inc. (GIP)
Start Date
Mar 29, 2023
End Date
Sep 5, 2023
Actual Cost
$941,000.00
Contact
[email protected]
INSTALLATION OF TYPE D PXO - HARBOUR FRONT DRIVE AND MARINA ACCESS ROADWAY. [2023] - C15-45-23(TR)
Map
Traffic
Installation of Type D PXO and raised crosswalk - Harbour Front Drive and Marina access roadway.
Estimated Construction
Aug 2023 - Jul 2024
Contact
[email protected]
IPS/PXO INSTALLATION: SANFORD AVENUE & HURON STREET [2023] - C15-45-23(TR)
Map
Traffic
IPS/PXO Installation (TBD): Sanford Avenue & Huron Street
Estimated Construction
Sep 2023 - Nov 2023
Contact
[email protected]
JAMES ST S VOID ADJACENT TO #'S 18, 28 & 32, BETWEEN MAIN ST AND KING ST - INVESTIGATION AND REPAIR [2023] - RFQ-01-22
Map
Road
Void Investigation, repair with road and sidewalk restoration
Estimated Construction
Dec 2022 - Sep 2024
Contact
[email protected]
JONES ST - DUNDURN ST N TO WEST END [2023] - C15-24-23 (HSW)
Map
Road
Road and sidewalk reconstruction
Sanitary
Sewer lateral replacement
Storm
Storm Sewer Installation
Water
Water Distribution System Replacement
Contractor
Wesroc Construction Ltd.
Start Date
Aug 14, 2023
End Date
Nov 27, 2023
Actual Cost
$1,611,000.00
Contact
[email protected]
KENILWORTH ACCESS - ROCKFALL DRAPERY MESH [2023] - C15-71-22 (H)
Map
Structure
Rockfall Drapery Mesh Installation
Contractor
Premier North Ltd.
Start Date
Aug 8, 2023
End Date
Nov 29, 2023
Actual Cost
$935,000.00
Contact
[email protected]
KIRBY AVE - HIGHWAY NO. 8 TO EAST END OF STREET & HUNTS DR - KIRBY AVE TO EAST END OF STREET [2022] - C15-63-22 (H)
Map
Road
Road resurfacing
Contractor
Coco Paving Inc
Start Date
May 1, 2023
End Date
Jun 23, 2023
Actual Cost
$652,000.00
Contact
[email protected]
LARGE DIAMETER WATERMAIN REHABILIITATION: KENILWORTH RESERVOIR TUNNEL WATERMAIN [2023] - C13-10-22
Map
Water
The external repair of 283 m of the Kenilworth Transmission Watermain
Contractor
Clearway Construction Inc.
Start Date
Mar 21, 2023
Estimated Construction
Jan 2022 - Apr 2024
Actual Cost
$5,090,669.89
Contact
[email protected]
LARGE VALVE INSTALLATION: NORTH OF THE GREENHILL RESERVOIR (HDR1B) [2023] - C15-43-22 (W)
Map
Water
Large Valve Installation
Estimated Cost
$400,000.00
Contact
[email protected]
LARGE VALVE REPLACEMENT (HC10V055, HC10V054,HC11V052, HD06V031,HD09V051, HC11V050 AND HD13V056): FENNELL AT EAST 12TH, EAST 17TH ST, AT UP WENTWORTH, AT EAST 34TH, AT UPPER OTTAWA, AND S/O SANDALWOOD [2023] - C15-68-22 (W)
Map
Water
Large Valve Replacement
Contractor
Deso Construction
Start Date
Apr 5, 2023
Estimated Construction
Apr 2023 - Jun 2024
Actual Cost
$2,134,000.00
Contact
[email protected]
MARION AVE - LONGWOOD RD S TO DROMORE CRES [2023] - C15-28-23 (HW)
Map
Road
Road and sidewalk reconstruction
Sewer Service Line
Sanitary Sewer Service Line Replacement & Separation
Water
Water System Distribution Replacement
Contractor
Wesroc Construction Ltd.
Start Date
Apr 17, 2023
End Date
Nov 24, 2023
Actual Cost
$3,448,000.00
Contact
[email protected]
MOUNTAIN PARK AVE PHASE 01 - UPPER WENTWORTH ST TO PARKING LOT EAST OF POPLAR AVE, AND MOUNTAIN BROW TRAIL ENHANCEMENTS (WITHIN EASTMOUNT NEIGHBOURHOOD) [2023] - C15-34-22 (HW)
Map
Road
Road resurfacing and pedestrian facility enhancements
Water
Water Distribution Sytem Improvement
Contractor
Mastercrete Construction Inc.
Start Date
Mar 27, 2023
End Date
Sep 25, 2023
Actual Cost
$2,387,000.00
Contact
[email protected]
OSLER DRIVE OUTFALL AT GRANT BLVD [2023] - C15-16-23 (S)
Map
Storm
Outfall replacement
Contractor
Gedco Excavating
Start Date
Oct 11, 2023
Estimated Construction
Oct 2023 - Dec 2023
Actual Cost
$652,000.00
Contact
[email protected]
RETAINING WALL RW0447 - WEIRS LANE, 392M NORTH OF JOHNSON AVE - W/S [2023] - C15-49-23 (H)
Map
Structure
Retaining Wall Replacement
Contractor
Oakridge Group Inc.
Estimated Construction
Nov 2023 - Dec 2023
Actual Cost
$617,000.00
Contact
[email protected]
SATELLITE CITY TRUNK PIPELINE CIPP REHABILITATION FROM MUD ST W TO QUIGLEY RD (NORTH OF VEEVERS DR) [2022] - C13-22-19 (2022)
Map
Sanitary
Major Trunk Sewer Rehabilitation
Contractor
Insituform Technologies
Estimated Construction
Jun 2023 - Jun 2021
Estimated Cost
$8,880,000.00
Contact
[email protected]
SCENIC DR - MOHAWK TO CHATEAU [2023] - C15-59-23 (HS)
Map
Road
Road reconstruction
Contractor
Green Infrastructure Partners Inc. (GIP)
Start Date
Sep 20, 2023
Estimated Construction
Sep 2023 - Jun 2024
Actual Cost
$4,359,000.00
Contact
[email protected]
SEWER REGULATOR REHABILITATION [2023] - C15-52-23 (IR)
Estimated Cost
$504,000.00
Contact
[email protected]
SHERMAN - WILSON TO SOUTH END (LRT-ENABLING) [2023] - C15-32-23 (HW)
Map
Road
Road resurfacing
Sewer Service Line
Sewer Service Line Replacement
Water
Water Distribution System Improvement (LRT Enabling Project)
Contractor
Deso Construction
Start Date
Sep 25, 2023
End Date
Nov 28, 2023
Actual Cost
$4,730,721.00
Contact
[email protected]
SOUTHCOTE RD - GARNER RD (EXCLUDING INTERSECTION OF GARNER RD) TO HWY 403 [2022] - C15-19-22 (HSW)
Map
Road
Road reconstruction, urbanization and widening
Storm
Storm Water Upgrades
Water
Watermain Distribution Extension
Contractor
Coco Paving Inc
Start Date
Nov 7, 2022
Estimated Construction
Oct 2022 - Aug 2024
Actual Cost
$14,916,000.00
Contact
[email protected]
TRAFFIC SIGNAL MODIFICATION AND ASSOCIATED WORKS: PRITCHARD RD & RYMAL ROAD [2023] - C15-45-23(TR)
Map
Traffic
Modernize existing traffic signal to include underground conduits and new traffic infrastructure BP
Estimated Construction
Aug 2023 - Nov 2023
Contact
[email protected]
WATERMAIN STRUCTURAL LINING: HILLYARD ST TO WENTWORTH ST N [2023] - C13-01-20 (2023)
Map
Water
Watermain Structural Lining
Contractor
Fer-Pal Construction
Start Date
Apr 6, 2023
End Date
Sep 27, 2023
Contact
[email protected]
WATERMAIN STRUCTURAL LINING: OTTAWA ST S/ LONDON ST S/ EDGEMONT ST S [2023] - C13-01-20 (2023)
Map
Water
Hamilton Water Watermain Lining Priority
Contractor
Fer-Pal Construction
Start Date
Mar 27, 2023
End Date
Sep 27, 2023
Contact
[email protected]
WATERMAIN STRUCTURAL LINING: PARK ROW S - LAWRENCE RD TO MAPLE AVE [2023] - C13-01-20 (2023)
Map
Water
Hamilton Water Watermain Lining Priority
Contractor
Fer-Pal Construction
Start Date
Mar 27, 2023
End Date
Sep 27, 2023
Contact
[email protected]
WATERMAIN STRUCTURAL LINING: WEST 19TH ST - MOHAWK RD W TO ELMWOOD AVE [2023] - C13-01-20 (2023)
Map
Water
Hamilton Water Watermain Lining Priority
Contractor
Fer-Pal Construction
Start Date
Mar 27, 2023
End Date
Sep 27, 2023
Contact
[email protected]
WATERMAIN STRUCTURAL LINING:GLOVER RD - 50M NORTH OF GLOVER ACCESS RD S TO 482 GLOVER RD [2023] - C13-01-20 (2023)
Map
Water
Watermain Structural Lining: 403 CROSSING
Contractor
Fer-Pal Construction
Start Date
Jul 10, 2023
End Date
Sep 27, 2023
Contact
[email protected]
WATERMAIN STRUCTURAL LINING:SOUTH DR - HWY 5 W TO SOUTH END [2023] - C13-01-20 (2023)
Map
Water
Watermain Structural Lining
Contractor
Fer-Pal Construction
Start Date
Jul 10, 2023
End Date
Sep 27, 2023
Contact
[email protected]
WELLINGTON ST STORM OUTFALL - BURLINGTON ST - HARBOUR [2023] - C15-53-22 (IR)
Map
Storm
Storm Outfall Rehabilitation
Start Date
Jan 9, 2023
Estimated Construction
Jan 2023 - Dec 2023
Actual Cost
$1,268,000.00
Contact
[email protected]